Sixty pylon Richborough Connection line now complete

The final pylon

The 20km high voltage line of 60 pylons between Richborough and Canterbury has now been completed.

The new National Grid 20km line will connect Nemo Link – high voltage electricity cables under the sea between the former Richborough Towers site and Herdersbrug in Belgium – into the high voltage electricity network.

The new line, completed by National Grid and its contractors Murphy Eltel Joint Venture, is the first to be built in Kent for 25 years.

A total of 260km of high voltage cables have now been placed on the pylons and have been tested, paving the way for the final testing and commissioning of the Nemo Link® interconnector.

The construction work, carried out by 250 workers at the peak of operations, involved more than 6,000 crane lifts to put the pylons in place for a route that crosses eight roads, three rivers and three rail lines in its journey across the county.

The first pylon for the Richborough Connection and the route

Graham Dolamore, project director for National Grid, said: “The completion of the Richborough Project is a significant milestone in the programme for these two projects which will allow power to flow between Britain and Belgium early next year, providing security of supply and greater opportunities for the UK to trade with wider European energy markets.

“I’m proud to have been a part of this project and of the fact that we’ve worked closely with landowners and communities to get the connection built on time and with minimal disruption. It is another demonstration of the crucial role National Grid plays in making sure people across Kent and far beyond have the energy they need, when they need it.”

Wreath laid at the top of the first pylon by workers

Shane Jestin, Murphy Eltel Construction director, said: “It has been a tough but successful job all round, thanks to the hard work of all those involved. We’ve carried out more than 6,000 lifts and managed to hit challenging project deadlines thanks to a mix of thorough planning and excellent delivery.”

More than 750,000 working hours were spent building the overhead line. Works were also carried out at Canterbury North substation and the new Richborough substation with both extended and equipment either installed or upgraded. The work was carried out by ABB and Siemens.

Some small-scale works will be carried out over the coming months in preparation for the removal of UK Power Network’s overhead lines in 2020.

Read here: Nemo Link team discovered 985 potential unexploded bombs on cable link route to Pegwell