Consultation on new turbine proposals for Thanet Offshore Windfarm

Thanet Offshore Windfarm

Vattenfall, the developer of the proposed Thanet Extension Offshore Wind Farm is seeking views from residents in Thanet and Sandwich on plans for up to 34 wind turbines, up to 250 metres tall, to be installed at the site.

Wind turbines that tall are not yet commercially available but Vattenfall says it is confident that rapid technological development will deliver in time for deployment in the early 2020s

Some 70,000 residents in the area have been, or are due to be, sent a newsletter about Vattenfall’s proposals. This is ahead of a statutory consultation on the Preliminary Environmental Information Report (PEIR) which sets out a ‘maximum design envelope’ and considers the potential impacts of the project during construction and operation.

In addition, Vattenfall, which runs its Kent offshore wind farm operations out of Ramsgate, where 70 people work, will run 15 public events in the area through December and early January.

Helen Jameson, Vattenfall’s Project Manager for Thanet Extension, said: “We hope that Thanet Extension will be operational by the end of 2021, 11 years after the existing wind farm started to operate.

“The rapid growth in wind turbine productivity and the incredible rate of innovation means we could produce more than the current wind farm whilst deploying only a third the number of turbines. This approach will continue the industry’s strong record in significant cost reduction by offering cheap, clean, green electricity for the British consumer.

“There will be impacts though, both positive and negative, onshore and off, and that is why we are keen to understand the views of residents, businesses and organisations before we submit a final proposal next Spring to the Planning Inspectorate. We think we pose an interesting question: what is the right balance of turbine numbers and height? Fewer and taller or more but smaller?”

If approved by the government, Thanet Extension will expand the existing 100 wind turbine, 300MW Thanet Offshore Wind Farm. Despite having fewer turbines, the extension will produce more power than the seven-year-old project which was, at the time of its inauguration in 2010, the world’s largest offshore wind farm.

PROJECT FIGURES

Number of turbines: Up to 34
Installed Capacity: up to 340MW
Turbine size (capacity and height range). Maximum height 250m. Individual turbine capacity dependent on technology. 10MW and 12MW assumptions used as basis for EIA and illustrated in PEIR.
Cables onshore (number and length) up to 4 circuits, each comprised of 3 individual cables (12 cables in total), either trenched or surface lay and cover. Onshore cable route distance of ~2,5km
Cables offshore (number and length): 4 cables at 28km maximum distance
Landfall Location: Pegwell Bay
Grid Connection and substation: Substation at Richborough Port, up to two 400kV connection cables between substation and grid connection at Richborough Energy Park

Find out more about Vattenfall here